How-to: Generating Gantt chart reports for estimated, planned, and actual hours of WBS lines

Introduction

This report displays the estimated, planned, and actual hours for WBS lines related to the deliverables of a project.

Requirements and prerequisites

To be able to generate reports, users must ensure the following:

How do I generate Gantt chart reports for estimated, planned, and actual hours of WBS lines?

  1. On the Reporting services integration: Management page, select the relevant report. For more information, see Configuring a report parameter – Reporting services integration.
  2. Select the Parameters tab to define the respective parameters, as displayed in the following:

     

  3. To add or view the report on a project card as web part, select the Show as web part check box, as displayed in the following: 
     


  4. Click Save to save the defined parameters and click View to see the report. The following is an example of the report:

Related documents

 

 

     
 Main Category: Support Product Know How  Document Type: Online help main
 Category: On-line help files  Security  level: All - 0
 Sub category: Details  Document ID: 23.532.910
 Assortment:  Date: 03-05-2012
 Release: 249  Attachment:
 Disclaimer