Advanced button for Tasks/Requirements section
Introduction
This document provides you the information about the Advanced button in the Tasks/Requirements section of the overview of resource planning and tasks.
Menu path
- Go to Projects ➔ Planning ➔ Resource planning, or Manufacturing ➔ Planning ➔ Resource planning, and then click Advanced.
Fields
Filter section
Warehouse, Job groups, Resource, Assortment, Activity, Project
Click Select to select one or more projects, job groups, resources, assortments, activities, or projects to display the tasks linked to the selection(s) in the overview.
- - This indicates that none of the project, job group, resource, assortment, activity, or project has been selected.
- - This indicates that at least one project, job group, resource, assortment, activity, or project has been selected.
Show: Planned
Select this check box to show the planning for the expanded the tasks.
Based on scenario
Select this check box to display the tasks based on MRP scenarios. Once selected, Scenario: MRP and the Details button at the overview of resource planning and tasks will be enabled. For more information, see Overview of resource planning and tasks. On the other hand, the Sales orders and Production orders check boxes will be disabled,
Scenario: MRP
Type or select an MRP scenario to display the tasks linked to the selected MRP scenario. This is mandatory. Once selected, the Details button at the overview of resource planning and tasks will be enabled. For more information, see Overview of resource planning and tasks.
Note: This field is enabled only when you select the Based on scenario check box.
Sales orders
Select the check box under the Not authorized or Authorized column to display the sales orders with the corresponding status. Click Select to select one or more selection codes for the sales orders. The selection codes are booked by sales orders with the corresponding status and linked to the labor hour requirements.
Note: This check box is enabled only when you clear the Based on scenario check box.
Production orders
Select the check box under the Not authorized or Authorized column to display the production orders with the corresponding status. Click Select to select one or more selection codes for the production orders. The selection codes are booked by production orders with the corresponding status and linked to the labor hour requirements.
Note: This check box is enabled only when you clear the Based on scenario check box.
Buttons
OK
Click this to save your selections and exit the screen.
Close
Click this to exit the screen without saving.
Related document
Main Category: |
Attachments & notes |
Document Type: |
Support - On-line help |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
14.792.101 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
|
Attachment: |
|
Disclaimer |