MRP calculation
Menu path
System ➔ Checks ➔ MRP calculation
Introduction
This document provides you the steps to rectifying
inconsistencies in MRP (Materials Requirements Planning).
The MRP calculation function compares the MRP data with that
of the transaction data. If inconsistencies are found, this function rebuilds
the missing data and corrects it in the MRP table. This is useful when data
corruption occurs and a user wants to recalculate the MRP.
Via the menu path, the transaction types to be included in
the MRP checking can be specified, such as the purchase orders, sales orders,
quotations, hour entries, and order planning. The delivery dates of all open
orders can also be modified.
What version are you using?
The information in this document is applicable to product
update 407 and higher. If you have versions lower than this, certain features
explained here will not be applicable.
How do I perform the MRP calculation?
- In the MRP calculation screen, define and select the relevant fields and check
boxes.
- Click Calculate.
- In
the Generate section, the Done status will be displayed to
indicate that the calculation is completed.
- Click
Close.
Fields
Option section
Warehouse
Type or select a warehouse to generate the MRP calculation
for items linked to that warehouse.
Note: This field is disabled if the Last modified
check box is selected.
Last modified
Select this check box to generate the MRP calculation for
orders that were entered or modified after the MRP calculation was last generated.
By default, this check box is selected. Clear the check box to enable the
rectification for all orders. When this check box is cleared, you can also
specify what you want to correct: purchase orders, sales orders, and/or
quotations.
Order: Date
Type or select a date or a range of dates to generate the
MRP calculation for orders created within the specified dates. Select the All
check box to generate the MRP calculation for any order dates.
Note: This field is disabled if the Last modified
check box is selected.
Assortments
Click this to display a list of all assortment types. You
will see the Assortments screen. Select the assortment(s) required, then
click Select. Click Close to return to the previous screen. You
will see a green check
mark next to the Assortments button.
Note: Assortments need to be defined at System ➔ General ➔ Item data settings, or at Inventory ➔ Items ➔ Assortments before being made available here.
Note: This field is disabled if the Last modified
check box is selected.
Item
Type or select an item or a range of items to generate the MRP
calculation for the item(s). Select the All check box to generate the
MRP calculation for all items.
Note: This field is disabled if the Last modified
check box is selected.
Include section
Purchase orders
Select this check box to generate the MRP calculation
for purchase orders only.
Note: This check box is disabled if the Last
modified check box is selected.
Sales orders
Select this check box to generate the MRP calculation for
sales orders only.
Note: This check box is disabled if the Last
modified check box is selected.
Quotations
Select this check box to generate the MRP calculation for
quotations only.
Note: This check box is disabled if the Last
modified check box is selected.
Change: Fulfilment date
Select this check box to assign a new delivery date (the
current date) to all open orders with a delivery date in the past (before
current date).
Note: This check box is disabled if the Last
modified check box is selected.
Hour entries
Select this check box to fix incorrect or missing records
related to hour entries. For example, by selecting this option, the MRP
calculation updates the hour entries with end times 23:59:59 to actual
(realized) hour end times, and also updates the start and end times of the
realized records where they were null.
Planning
Select this check box to do the following:
-
correct sales orders with wrongly planned delivery dates, and
- rectify wrong schedules of persons because of changed hour
realizations.
Invoice proposal: Debtor
Select this check box to do the following:
- update invoice proposal records where the debtor value is missing
so that the debtor is the same in the invoice proposal as in the sales order,
and
- update the project debtor to ensure it is consistent with the invoice
debtor in the sales order.
Generate section
This section displays the progress of the MRP calculation
after the Calculate button is clicked.
Buttons
Calculate
Click this to start the MRP calculation.
Close
Click this to exit.
Related document
Main Category: |
Attachments & notes |
Document Type: |
Online help main |
Category: |
|
Security level: |
All - 0 |
Sub category: |
|
Document ID: |
12.251.431 |
Assortment: |
Exact Globe+
|
Date: |
26-09-2022 |
Release: |
|
Attachment: |
|
Disclaimer |