Maintain: Project (Schedule)

[Project: Projects, Project schedules, Maintenance]

Project

Choose a project for which you want to view/create a schedule and click 'Save'. The created project schedule (if any) will be displayed on the schedule lines.  To create a new project schedule, right-click on 'Start' and now you can choose if you want to insert an activity, a phase, an employee resource or a machinery resource.

Insert an activity

You can choose to insert a new activity in the project by selecting 'New: Activity'.  

Matrix for data entry

Entity Code

A suggestion is done for the sequence number of the activity, if you have entered an increment factor in [Project: File, Company settings, Project settings].   However, you can change this entity code. 

Description

Give a description of the activity.

Start date/Start time

Enter the start date/time on which the activity is scheduled to start.

End date/End time

Enter the end date/time on which the activity will be completed. 

Budget quantity

Enter the budget quantity that allocated for each activity in the project.

Hour category

Choose the hour category you want to link to this activity.

Unit

Choose the unit you want to link to this activity.

Location

Enter the location you want to link to this activity.

Block

You can 'block' the activity by enabling this setting.

Critical

You can make this activity 'critical' by enabling this setting.

Priority

Enter the priority of the activity.

Date ready

Enter the date on which the activity is done.

After you have inserted an activity, you can link something to this activity. You can choose from three options: to insert another activity, an employee resource or a machinery resource. 

Insert a phase

You can choose to insert a new phase in the project by selecting 'New: Phase list definition'.   

Matrix for data entry

Entity code

A suggestion is done for the sequence number of the phase, if you have entered an increment factor in [Project: File, Company settings, Project settings].   However, you can change this entity code. 

Phase code

Enter the phase you want to add to the project.

Start date

Enter the start date for this phase.

End date

Enter the end date for this phase.

After you have inserted a phase, you can link something to this phase as well.  You can choose from three options: to insert an activity, an employee resource or a machinery resource.

Insert an employee resource

You can choose to link an employee to the project by selecting 'New: Employee (Resource)'. This works the same way as inserting an activity. Only you enter a resource code (entity code) and select an employee instead of an activity's entity code and a unit.  Please take note that you are unable to link anything to an employee. 

Insert a machinery resource

You can choose to insert a machinery in the project by selecting 'New: Machinery (Resource)'. This works the same way as inserting an activity. Only you enter a machinery code (entity code) and select a machinery instead of an activity's entity code and a hour category.   Please take note that you are unable to link anything to a machinery. 


Project Manual > Contents > Creating and reviewing projects and project budgets > Creating a project schedule > [Project: Projects, Project schedules, Maintenance]

     
 Main Category: Support Product Know How  Document Type: Online help main
 Category: On-line help files  Security  level: All - 0
 Sub category: Details  Document ID: 17.991.597
 Assortment:  Date: 11-11-2008
 Release:  Attachment:
 Disclaimer

Tags
No tags added